Infrastructure Development of Phase 1

Laying of Water supply lines has also been started along with the sewerage lines. 33% sewerage lines and 25% water supply lines have been completer so far.
Similarly 50% roads of Block K has also been defined and are being developed. Span of work is being increased to Block J and the works shall start in next 2 weeks. Access road has been completed, its last patch is being metaled at the moment.
Block C and 300ft Wide main access road is also under progress and its sub base has been completed. A contract for the development of Block G and is underway; and development of remaining blocks of Phase 1 shall start immediately after the completion of aforementioned blocks.
Telephone Exchange of 300 connections has been installed by PTCL at site and is fully functional.

This entry was posted in Projects Updates and tagged , . Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

Close
Stay in touch with Qurtaba