Development Work in Phase 1

Posted ago by Imran

Development works on Access road has been started, drainage system on both sides of the road is being made at the moment, around 6000 RFT boundary wall has been established around phase 1 so far. Construction of another water tank in Block K has also started. construction of Main Entrance Gate is also continued.

Development work continues despite long Holidays of Eid ul Adha

Posted ago by Imran

Development work continues despite long Holidays of Eid ul Adha, Boundary wall around Phase 1 is being established at a very quick speed, same is the case with Main entrance complex. Office construction of contract is complete and now fully functional. Form work on the top bowl of Overhead Water tank is almost completed.

Development Current Updates

Posted ago by Imran

Following Development Activities have been performed during the past 1 month. Although the progress had been slow due to monsoon constructional activities were carried out at maximum possible speed.

  1. Form work for remaining portion of the overhead water tank.
  2. concrete of first floor of block D’s Masjid.
  3. start of construction activity on Boundary Wall around the project.
  4. continuation of construction of Main Entrance Complex.
  5. Earth Work and Roads construction in Block A, B and C.

Qurtaba City Development Pics (11)

Development Updates

Posted ago by Imran

Qurtaba City Development Pics (2)Development activities on different locations of phase 1 are underway, Main shaft of overhead Water tank is almost completed, form work of the top area is currently being done. Construction of Main entrance complex has also started, Columns of Majid of Block D are also being constructed with optimum speed. Cutting of high level areas of a portion of Block C is also being done. “

Development activates have been started on site by the contractor ACC

Posted ago by Imran

Development activates have been started on site by the contractor ACCP, Block B is currently being developed whereas labor camps, Site offices and soil testing for construction of another water tank in block K are also being executed. On the other hand construction of Main entrance gate, Masjid of D block and the water tank of the same block is also being constructed.”

Close
Stay in touch with Qurtaba